When a project is fully identified (depending on individual company policy) it is loaded into the Muli system. This could be when major estimating effort is intended or when the project is won.
The first activity is to load the project master record, which effectively sets up all the controls that will be imposed on the project throughout its life. Project Master Maintenance (2.1)
How the contract price was developed, determines the way in which the budget is loaded, either directly from the Muli estimate, or utilizing a skeleton and then manually loaded. Budget Maintenance Routine (2.4)
It is important that the budget is loaded with separate identified values for each of the individual orders and subcontracts that need to be let, and for major subcontracts the major elements. This leads to the: Detailed Budget Report (2.5)
Variations are the first of many documents that are produced by the Muli system to ensure that no commitment leaves the organization that is not recorded as part of the project database.
Note: From a control perspective, Muli recommends the first variation written is the hand back to the client of any PC Sums and the raising of ball park values for the contract stated PC values for each item. Thus the client has to approve the PC Variation for a budget to exist and therefore to place the order. See Variation Master Report (2.7)
Variations are processed through 3 stages: